HOME / Business / Business Model

Business

"Our business model is based on the following Financial Assumptions"


Project Cost Estimate Particulars Rs. Mn
Land 5.63
Civil works 36.00
PV Modules 252.00
Module mounting structure 45.00
BOS including Combiner Box, 76.50
Invertors, data logging System etc.
Transmission Line (12 km) 8.10
Terminal equipments at evacuation point 5.40
Prel. & Pre Operative Expenses 3.38
Interest During Construction (IDC) 13.50
Working Capital Margin (WCM) 4.50
Total 450

Assumptions Unit Value Data source
Installed capacity MW 5 Proposed originally
Working days Days 365 Industry Norms
Plant load factor % 18.65% Commitment from vendor
Average capital cost/MW INR 90 million Assumed
O&M expenses INR million 1.16 CERC Re tariff regulation 2013
Equity investment % 30 Assumed
O&M expenses (on project) % 26 CERC Re tariff regulation 2013
Escalation in O&M % 5.72 CERC RE tariff regulation 2013
Panel output degradation( P.A.) % .80 Vendor commitment
Interest on term loan % 13 CERC RE tariff regulation
Loan repayment period/years Year 12 As per assumption workings
Book depreciation rate( weighted average) % 3.6 CERC RE tariff regulation
Book depreciation limit % 90  
Depreciation as per IT act - WDV % 15 As per IT act for calculations
Income tax regular % 32.45 Budget 2010-2011 (India)
Minimum alternate Tax % 20.01 Budget 2010-2011
Incentive
Tax holidays Year 10 Under IT section 80IA
Energy Generation
Generation GWHorMU 18.1687

Tariff structure assumptions – Renewable energy certificate + APPC

Year 20122013201420152016201720182019202020212022
20132014201520162017201820192020202120222023
Appc/INR unit 2.372.492.612.742.883.023.183.333.503.683.86
Rec/INR/unit 9.309.309.309.309.306.006.006.006.006.005.00
Total cost 11.611.711.912.012.19.029.189.339.509.688.86
INR/UNIT 79140

With the above Technology selection and Financial Assumptions our Project IRR is 15.01% and our Equity IRR is 18.90%


Our Strategic Partners