HOME / Business / Business Model
Business
"Our business model is based on the following Financial Assumptions"
Project Cost Estimate Particulars |
Rs. Mn |
Land |
5.63 |
Civil works |
36.00 |
PV Modules |
252.00 |
Module mounting structure |
45.00 |
BOS including Combiner Box, |
76.50 |
Invertors, data logging System etc. |
|
Transmission Line (12 km) |
8.10 |
Terminal equipments at evacuation point |
5.40 |
Prel. & Pre Operative Expenses |
3.38 |
Interest During Construction (IDC) |
13.50 |
Working Capital Margin (WCM) |
4.50 |
Total |
450 |
Assumptions |
Unit |
Value |
Data source |
Installed capacity |
MW |
5 |
Proposed originally |
Working days |
Days |
365 |
Industry Norms |
Plant load factor |
% |
18.65% |
Commitment from vendor |
Average capital cost/MW |
INR |
90 million |
Assumed |
O&M expenses |
INR million |
1.16 |
CERC Re tariff regulation 2013 |
Equity investment |
% |
30 |
Assumed |
O&M expenses (on project) |
% |
26 |
CERC Re tariff regulation 2013 |
Escalation in O&M |
% |
5.72 |
CERC RE tariff regulation 2013 |
Panel output degradation( P.A.) |
% |
.80 |
Vendor commitment |
Interest on term loan |
% |
13 |
CERC RE tariff regulation |
Loan repayment period/years |
Year |
12 |
As per assumption workings |
Book depreciation rate( weighted average) |
% |
3.6 |
CERC RE tariff regulation |
Book depreciation limit |
% |
90 |
|
Depreciation as per IT act - WDV |
% |
15 |
As per IT act for calculations |
Income tax regular |
% |
32.45 |
Budget 2010-2011 (India) |
Minimum alternate Tax |
% |
20.01 |
Budget 2010-2011 |
Incentive |
|
|
|
Tax holidays |
Year |
10 |
Under IT section 80IA |
Energy Generation |
|
|
|
Generation |
GWHorMU |
18.1687 |
|
Tariff structure assumptions – Renewable energy certificate + APPC
Year |
2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 |
2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 |
Appc/INR unit |
2.37 | 2.49 | 2.61 | 2.74 | 2.88 | 3.02 | 3.18 | 3.33 | 3.50 | 3.68 | 3.86 |
Rec/INR/unit |
9.30 | 9.30 | 9.30 | 9.30 | 9.30 | 6.00 | 6.00 | 6.00 | 6.00 | 6.00 | 5.00 |
Total cost |
11.6 | 11.7 | 11.9 | 12.0 | 12.1 | 9.02 | 9.18 | 9.33 | 9.50 | 9.68 | 8.86 |
INR/UNIT |
7 | 9 | 1 | 4 | 0 |
With the above Technology selection and Financial Assumptions our Project IRR is 15.01% and our Equity IRR is 18.90%